U.S. Secretary of Energy Chris Wright on Wednesday issued an emergency order permitting PJM Interconnection, in coordination with Talen Energy Corporation, to operate a generating unit at a Maryland power plant.
The Department of Energy said the directive is intended to minimize the risk of energy shortfalls in 13 states and the District of Columbia, and to stabilize the mid-Atlantic power grid.
The order allows the use of Unit 4 at the Wagner Generating Station in Anne Arundel County to meet anticipated electricity demand. PJM submitted the application for the emergency directive on Oct. 23, the department said.
According to the agency, PJM relied on the generating unit during periods of unusually high temperatures earlier in the summer, utilizing its remaining operating hours. PJM recently reaffirmed to the department that the unit is still needed to manage high electricity demand and strengthen grid reliability.
Wright previously granted requests from PJM to run the unit beyond its normal operating limit. “Energy shortfalls for 65 million Americans are simply unacceptable,” Wright said in the announcement.
The renewed order is effective from Nov. 18 through Dec. 31.