- What it does
The Environmental Protection Agency (EPA) is approving State Implementation Plan (SIP) revisions submitted by the State of Connecticut for the 2015 ozone National Ambient Air Quality Standard (NAAQS). These revisions certify the adequacy of the SIP to satisfy the nonattainment new source review permitting requirements of the Clean Air Act (CAA) for the reclassification of the Greater Connecticut area to moderate nonattainment for the 2015 ozone NAAQS, and certify the emission statement program satisfies CAA requirements for the initial nonattainment designations and the reclassification to moderate nonattainment for the 2015 ozone NAAQS. This action is being taken in accordance with the CAA.
The Environmental Protection Agency's summary, as published in the Federal Register.
- What changed in the regulation
1 part of Title 40 of the Code of Federal Regulations:
Wording on eCFR: the day before it took effect and from the day it took effect (first part listed).
- Compared with
The Environmental Protection Agency has published 256 final rules in 2026 so far, compared with 263 in all of 2025.
Counted by the Tribune from Federal Register records since Jan. 1, 2025.
- What happens next and when
This rule is effective on May 22, 2025.
The agency's dates, word for word.
The record as published
| Document number | 2025-06610 |
|---|---|
| Action | Final rule. |
| Agencies | Environmental Protection Agency |
| Published | April 22, 2025 |
| Effective date | May 22, 2025 |
| Docket | EPA-R01-OAR-2024-0193 |