Building for the Future Through Electric Regional Transmission Planning and Cost Allocation
Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register April 28, 2025. Document 2025-06941. Updated Nov. 24, 2026.
- What it does
In this order, the Federal Energy Regulatory Commission addresses arguments raised on rehearing, grants clarification, in part, and denies clarification, in part, of Order No. 1920-A, which addressed arguments raised on rehearing of, set aside, in part, and clarified Order No. 1920. Order No. 1920 required transmission providers, inter alia, to conduct Long-Term Regional Transmission Planning to ensure the identification, evaluation, and selection, as well as the allocation of the costs, of more efficient or cost-effective regional transmission solutions to address Long-Term Transmission Needs.
The Federal Energy Regulatory Commission's summary, as published in the Federal Register.
- What changed in the regulation
1 part of Title 18 of the Code of Federal Regulations:
Wording on eCFR: the day before it took effect and from the day it took effect (first part listed).
- Compared with
The Federal Energy Regulatory Commission has published 10 final rules in 2026 so far, compared with 14 in all of 2025.
Counted by the Tribune from Federal Register records since Jan. 1, 2025.
- What happens next and when
The effective date of the document published on December 6, 2024 (89 FR 97174), is confirmed: January 6, 2025.
The agency's dates, word for word.
- Check it yourself
The record as published
| Document number | 2025-06941 |
|---|---|
| Action | Order on rehearing and clarification. |
| Agencies | Energy Department; Federal Energy Regulatory Commission |
| Published | April 28, 2025 |
| Effective date | Jan. 6, 2025 |
Source: the Federal Register (public domain). The document in the Federal Register