Application for Presidential Permit Authorizing the Construction, Connection, Operation, and Maintenance of Facilities for Transmission of Electric Energy at International Boundaries
Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register May 16, 2025. Document 2025-08539. Updated Nov. 24, 2026.
- What it does
This DFR rescinds regulations regarding the applications for a presidential permit authorizing construction, connection, operation, and maintenance of facilities for transmission of electric energy at international boundaries.
The Energy Department's summary, as published in the Federal Register.
- What changed in the regulation
1 part of Title 10 of the Code of Federal Regulations:
Wording on eCFR: the day before it took effect and from the day it took effect (first part listed).
- Compared with
The Energy Department has published 18 final rules in 2026 so far, compared with 33 in all of 2025.
Counted by the Tribune from Federal Register records since Jan. 1, 2025.
- Before this
No earlier Federal Register document under regulation identifier 1901-AB68 since Jan. 1, 2025.
Since then:
- July 14, 2025 Direct final rule; delay of effective date. Application for Presidential Permit Authorizing the Construction, Connection, Operation, and Maintenance of Facilities for Transmission of Electric Energy at International Boundaries
- Sept. 11, 2025 Final rule; confirmation of effective date. Application for Presidential Permit Authorizing the Construction, Connection, Operation, and Maintenance of Facilities for Transmission of Electric Energy at International Boundaries
- What happens next and when
The final rule is effective July 15, 2025, unless significant adverse comments are received by June 16, 2025. Significant adverse comments oppose the rule and raise, alone or in combination, a serious enough issue related to each of the independent grounds for the rule that a substantive response is required. If significant adverse comments are received, notice will be published in the Federal Register before the effective date either withdrawing the rule or issuing a new final rule which responds to significant adverse comments.
The agency's dates, word for word.
A later document, published July 14, 2025, gives the effective date as May 16, 2025. See it
The record as published
| Document number | 2025-08539 |
|---|---|
| Action | Direct final rule ("DFR"); request for comments. |
| Agencies | Energy Department |
| Published | May 16, 2025 |
| Effective date | July 15, 2025 |
| Comments close | June 16, 2025 |
| Regulation identifier (RIN) | 1901-AB68 |
| Docket | DOE-HQ-2025-0011 |
| Significant (marked in the Federal Register) | Yes |
Source: the Federal Register (public domain). The document in the Federal Register