Revised Industry Codes and Standards for Production and Utilization Facilities
Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register June 6, 2025. Document 2025-10324. Updated Nov. 23, 2026.
- What it does
The U.S. Nuclear Regulatory Commission (NRC) has received a petition for rulemaking (PRM) from Thomas Basso on behalf of the Nuclear Energy Institute, dated January 22, 2025, requesting that the NRC revise its regulations to remove specific conditions, clarify a specific requirement, and incorporate requested code cases to the next revisions of regulatory guides 1.84 and 1.147, which will be incorporated by reference into the agency's rulemaking on industry standards. The petition was docketed by the NRC on March 6, 2025, and has been assigned Docket No. PRM-50-127. The NRC is examining the issues raised in PRM-50-127 to determine whether they should be considered in rulemaking. The NRC is requesting public comment on this petition at this time.
The Nuclear Regulatory Commission's summary, as published in the Federal Register.
- What it would change
1 part of Title 10 of the Code of Federal Regulations:
- What happens next and when
Submit comments by August 5, 2025. Comments received after this date will be considered if it is practical to do so, but the NRC is able to assure consideration only for comments received on or before this date.
The agency's dates, word for word.
The record as published
| Document number | 2025-10324 |
|---|---|
| Action | Petition for rulemaking; notice of docketing, and request for comment. |
| Agencies | Nuclear Regulatory Commission |
| Published | June 6, 2025 |
| Comments close | Aug. 5, 2025 |
| Docket | NRC-2025-0060 |
Source: the Federal Register (public domain). The document in the Federal Register