Fee Schedules; Fee Recovery for Fiscal Year 2025
Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register June 24, 2025. Document 2025-11544. Updated Nov. 22, 2026.
- What it does
The U.S. Nuclear Regulatory Commission (NRC) is amending the licensing, inspection, special project, and annual fees charged to its applicants and licensees. These amendments are necessary to comply with the Nuclear Energy Innovation and Modernization Act, which requires the NRC to recover, to the maximum extent practicable, approximately 100 percent of its annual budget, less certain amounts excluded from this fee recovery requirement. In addition, the NRC is making amendments to implement a reduced hourly rate for advanced nuclear reactor applicants and pre-applicants for certain activities as required by the Accelerating Deployment of Versatile, Advanced Nuclear for Clean Energy Act of 2024.
The Nuclear Regulatory Commission's summary, as published in the Federal Register.
- What changed in the regulation
2 parts of Title 10 of the Code of Federal Regulations:
Wording on eCFR: the day before it took effect and from the day it took effect (first part listed).
- Compared with
The Nuclear Regulatory Commission has published 35 final rules in 2026 so far, compared with 28 in all of 2025.
Counted by the Tribune from Federal Register records since Jan. 1, 2025.
- Before this
1 earlier Federal Register document under regulation identifier 3150-AK95 since Jan. 1, 2025.
Since then:
- What happens next and when
This final rule is effective on August 25, 2025.
The agency's dates, word for word.
The record as published
| Document number | 2025-11544 |
|---|---|
| Action | Final rule. |
| Agencies | Nuclear Regulatory Commission |
| Published | June 24, 2025 |
| Effective date | Aug. 25, 2025 |
| Regulation identifier (RIN) | 3150-AK95 |
| Docket | NRC-2023-0069 |
Source: the Federal Register (public domain). The document in the Federal Register