- What it does
The Federal Energy Regulatory Commission (Commission) proposes to remove from its regulations a rule that precludes the issuance of authorizations to proceed with construction activities with respect to natural gas facilities approved pursuant to section 3 or section 7 of the Natural Gas Act for a limited time while certain requests for rehearing are pending before the Commission.
The Federal Energy Regulatory Commission's summary, as published in the Federal Register.
- What it would change
2 parts of Title 18 of the Code of Federal Regulations:
- What happens next and when
Comments are due July 24, 2025.
The agency's dates, word for word.
- Check it yourself
The record as published
| Document number | 2025-11582 |
|---|---|
| Action | Notice of proposed rulemaking. |
| Agencies | Energy Department; Federal Energy Regulatory Commission |
| Published | June 24, 2025 |
| Comments close | July 24, 2025 |