Air Plan Approval; Ohio; Second Maintenance Plan for the Ohio Portion of the Campbell-Clermont, KY-OH SO2 Maintenance Area
Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register July 16, 2025. Document 2025-13343. Updated Nov. 21, 2026.
- What it does
The Environmental Protection Agency (EPA) is proposing to approve, under the Clean Air Act (CAA), the second 10-year maintenance plan submitted to EPA on November 7, 2024, by the Ohio Environmental Protection Agency (Ohio EPA) for the Ohio portion of the Campbell- Clermont Counties, Kentucky-Ohio maintenance area. The Ohio portion of this area consists of Pierce Township in Clermont County, Ohio. The plan addresses the second 10-year maintenance period for the 2010 sulfur dioxide (SO<INF>2</INF>) National Ambient Air Quality Standards (NAAQS). EPA is proposing to approve Ohio EPA's submittal for the area because it provides for the continued maintenance of the 2010 SO<INF>2</INF> NAAQS through the end of the second 10-year portion of the maintenance period.
The Environmental Protection Agency's summary, as published in the Federal Register.
- What it would change
1 part of Title 40 of the Code of Federal Regulations:
- What happens next and when
Comments must be received on or before August 15, 2025.
The agency's dates, word for word.
- Check it yourself
The record as published
| Document number | 2025-13343 |
|---|---|
| Action | Proposed rule. |
| Agencies | Environmental Protection Agency |
| Published | July 16, 2025 |
| Comments close | Aug. 15, 2025 |
| Docket | EPA-R05-OAR-2024-0542 |
Source: the Federal Register (public domain). The document in the Federal Register