Proposed rule

In Situ Recovery Monitoring and Decommissioning Timeliness

Built by the Tribune's code from the Federal Register. No AI wrote this page. Published in the Federal Register Sept. 10, 2026. Document 2026-18504. Updated Nov. 6, 2026.

What it does

The U.S. Nuclear Regulatory Commission (NRC) proposes to amend its regulations that govern the licensing of uranium mills and the disposition of tailings and waste that arise from the extraction and milling of uranium by issuing risk-informed requirements for groundwater protection at uranium in situ recovery (ISR) facilities. The NRC's current regulations are focused on conventional uranium milling and do not expressly address uranium extraction by the ISR process. Additionally, NRC proposes to amend its regulations that govern decommissioning timeliness for all licensees to provide additional flexibility for licensees to delay the initiation of decommissioning activities in situations where safety would not be impacted.

The Nuclear Regulatory Commission's summary, as published in the Federal Register.

What it would change

7 parts of Title 10 of the Code of Federal Regulations:

10 CFR 30, 10 CFR 40, 10 CFR 50, 10 CFR 52, 10 CFR 53, 10 CFR 70, 10 CFR 72

Before this

No earlier Federal Register document under regulation identifier 3150-AL48 since Jan. 1, 2025.

What happens next and when

Comments must be submitted electronically using https:// www.regulations.gov no later than 11:59 p.m. eastern time on October 13, 2026.

The agency's dates, word for word.

Document number2026-18504
ActionProposed rule and draft guidance; request for comment.
AgenciesNuclear Regulatory Commission
PublishedSept. 10, 2026
Comments closeOct. 13, 2026
Regulation identifier (RIN)3150-AL48
DocketNRC-2025-1204

Source: the Federal Register (public domain). The document in the Federal Register