The Government Accountability Office on Wednesday said none of 21 federal agencies that reported having data centers had fully met five requirements for acquiring and operating those centers. GAO asked Congress to renew the Federal Data Center Enhancement Act of 2023 or replace it with a new law.

Federal agencies use data centers for mission-critical data and operations. A 2023 law required the Office of Management and Budget to set minimum standards meant to ensure cybersecurity, resiliency, and availability, and agencies were required to carry them out. GAO said the law expired on Oct. 1, 2026, and that the budget office’s requirements expired on Sept. 30, 2026.

Agency compliance with data center requirements, August 2026
RequirementFully addressedPartially addressedNot addressed
Make key decisions at the agency level10110
Monitor operations with automated tools1092
Factor energy and water use into decisions050
Meet mission availability requirements2190
Meet information and physical security requirements4170
Source: U.S. Government Accountability Office.

Of 24 agencies covered by the Chief Financial Officers Act, 21 reported having data centers, the report said. As of August 2026, those agencies differed in how far they had built the five requirements into planning and management. GAO said it is not recommending changes to the agencies because the requirements have expired.

Ten agencies fully addressed a requirement to make key data center decisions at the agency level, and 11 addressed it only in part, according to the report. Ten fully addressed a requirement to monitor operations with automated tools, nine addressed it in part, and two did not address it. Nine agencies reported using automated tools, but the documents they provided did not always show that, GAO said.

No agency fully addressed a requirement to factor energy and water use into decisions. Five agencies with new data centers addressed that requirement only in part. The requirement did not apply to 16 agencies, the report said, because they reported no new data centers and the budget office did not require agencies to apply it to existing centers.

Two agencies fully addressed mission availability requirements, and 19 addressed them only in part. Many agencies reported meeting those requirements but did not show a process for managing risks to set the longest downtime, and how often downtime could occur, that their centers could tolerate, GAO said. Four agencies fully addressed information security and physical security requirements, and 17 addressed them only in part.

Congress passed the enhancement act in December 2023. The budget office set the five requirements in January 2025. Agencies were to meet them by Jan. 14, 2026, for centers they operate, with possibly later dates for centers run by contractors, the report said.

The act called for GAO to review compliance each year. This review was the third and last. Staff examined policies, procedures, and risk and security plans from the 21 agencies and spoke with agency officials, GAO said.

The report said advances in artificial intelligence, and wider use of it by agencies, have raised demand for the high-performance computing that data centers provide. It said Congress has introduced proposals on data centers that are meant, among other things, to address reporting of energy use. Those proposals apply more broadly to data centers nationwide and may also affect federal centers, GAO said.

If Congress renews or replaces the 2023 law, it could tell the budget office to update the requirements so agencies keep working on cybersecurity, resiliency, and availability, the report said. The suggestion to Congress remained open.

  1. Federal Data Centers: Congress Has an Opportunity to Improve Agencies' Acquisition and Operations — U.S. Government Accountability Office
How this article was made
Written with
Grok 4.7 (xAI)
Fact-checked by
Claude Sonnet 5.5 (Anthropic) — passed
Generated
Nov. 19, 2026, 8:13 a.m. ET
Sources used
1 official source, listed above
Article type
Standard

The AI wrote only from the sources listed. No human reporter was involved. Read our standards or compare the models in the AI Report Card.